2022 Investor Day Presentation
BRUCE POWER
Extending life and increasing
capacity without new infrastructure
Major Component Replacement (MCR) program and Asset Management
progressing, on-time and on-budget
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Unit 6
Unit 3
Unit 4
Unit 5
Unit 7
Unit 8
Project 2030 is the equivalent to adding a ninth generating unit
MW (NET PEAK)
7,200
7,150 7,160
7,060 7,060
7,000
6,975 6,975
6,800
6,740 6,790 6,810
6,600 6,490 6,534 6,580 6,580 6,595 6,590
+ PAST AND FUTURE INVESTMENT
⚫TC Energy has invested $2.3 billion
•
into Bruce Power since 2015
$2.3 billion planned to finish
MCR6 and MCR3 and fund the
current Asset Management work
through 2024
• $4.8 billion is planned for
refurbishment of Units 4, 5, 7 and
8, and the Asset Management
work beyond 2024
+ GOAL OF ACHIEVING PEAK SITE
OUTPUT OF 7,000 MW BY 2033
Continued asset optimization,
innovations and leveraging new
technology
By 2033, an additional ~600
MW is enough to power over
half a million homes
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034
Source: Bruce Power. Project 2030 represents 100% of Bruce Power facility.