Investor Presentaiton
Kinross Gold Corporation
Round Mountain
Phase S Optimization Highlights Higher Forecasted Returns
November 2023
.
•
•
Provides clarity around the next step for
Round Mountain - production expected to
extend through the end of the decade
Revised pit design has reduced the up-front
capex, leading to a higher-return, more
resilient outcome
Cost synergies with a potential higher-grade
Phase X underground, through shared
processing and G&A expenses
Incremental Phase S Estimates¹
Net Present Value (5%)
$170 million
IRR
Total Production
45%
~750 koz
Topo
KINROSS
New Phase S
Design
Old Phase S
"Design Removed
"from New Design
Initial Capital (project)²
$30 million
Initial Capital (strip)2
$140 million
Payback
2027
Total Material Mined
153 million tonnes
Strip Ratio
1. Economics at $1,850/oz Au; $85/bbl oil
2. Considered to be non-sustaining capital
2.1