Investor Presentaiton
Large Capital Projects
• Expect capital expenditures as a percentage of consolidated net sales to decrease to less than 4% after the completion of the
new brass foundry in Decatur, IL
• Three large capital projects expected to account for total capital spending around $150M and drive approximately $30M of
annualized incremental gross profit from cost savings and increased sales, after all are complete and at full run rate.
Benefits include accelerating product development, driving operational efficiencies, reducing duplicative expenses, increasing
revenue, expanding capabilities for American-made products and advancing our sustainability environmental initiatives
Large Valve Foundry
Brass Foundry
Specialty Valve Manufacturing
• Location: Chattanooga, TN
• Status: Construction completed with production
volumes ramping up
• Benefits: Expands domestic manufacturing capabilities
and leverages additive manufacturing technologies for
large gate and specialty valves to address anticipated
increase in demand for larger valve sizes and "Build
America, Buy America" products
•
Location: Decatur, IL
Status: Plant production ramp-up in 2023/2024 (1)
Benefits: Replacing century-old plant with new state-of-
the-art facility, using a new lead-free brass alloy, to
increase capacity, expand product development
capabilities, help achieve sustainability goals with lower
energy usage, reduced waste and enhanced safety
(1) Represents the timing of full project completion and not the timing of full annualized benefit from efficiencies and sales from new products.
• Location: Kimball, TN
•
Status: Plant consolidation and construction complete
with product volumes ramping up
Benefits: Consolidating multiple manufacturing facilities
for specialty valves and knife gates into one location
while also expanding domestic manufacturing
capabilities to address anticipated increase in demand
for "Build America, Buy America" products
MUELLER