Gas Master Plan
2
Gas Infrastructure Blueprint
ID
Pipeline Project
Length (km)/ Capacity
Diameter(in)
Description
2
OB-OB to Oben
100 / 42
1700
Provides security of Supply to the West
3
Calabar to Ajaokuta
365/
3000
(48,48,56)
Provides Security of Supply to North. Serves as
pre-investment for TSGP( Abia, Anambra en route)
4E
East Loop Onshore East
188/56
3500
Main Supply to Calabar CPF and the North
4W
East Loop Onshore West
56
3000
Supply to Bonny from the East Onshore
5E
East Loop Offshore East
32
1150
Supply to Calabar from offshore
5W
East Loop Offshore West
209/42
1700
Supply to Bonny from East offshore
11
Shagamu to Jebba
ELOPS
Escravos to Lagos
Offshore
265/(24,22)
200/42
390
Secure supply to Ogun, Osun, Oyo and Kwara
1250
Supply to Lagos via secure offshore route
ID
CPF Location
Capacity
COD Year
Description
A
Escravos
2395
2010
B
Ob-Ob
1700
2010
Serves North and West. Several phases of expansion, 2bcfd by 2012
Servers North and West. Several Phases of expansion.
Calabar
4500
2010
Main supply to Calabar and North
D
Bonny
1500
2013
Incremental capacity to LNG Plant
F
Forcados
3250
2020
G
Brass
1700
2011
1bcf required by 2012, successive expansion phases
Brass LNG Only
H
Olokola
2000
2012
No incremental capacity – LNG only foreseen
Source: IHS Gas Master Plan
Oando
The infrastructure blueprint highlights a number of gas pipeline and Gas
Central Processing Facilities (CPF) required to fulfil the domestic
utilisation requirements