MAPA PROJECT TIMELINE
July 2018
The Board of Directors
approved the MAPA
Project.
February 2019
Earth-moving works start.
May 2019
Contracts awarded for
construction companies, totaling
approximately US$ 680 million.
End of July 2021:
86% progress
Main equipment and parts on-site and
construction continues.
April 2011
Arauco's first
environmental studies
for MAPA Project.
October 2018
Arauco signed main equipment
contracts with Andritz and
Valmet
April 2019
On April 1st, 2019, Arauco signed an
ECA* agreement for a total of Eur 555
million. This financing is mainly
associated with the suppliers
contracts signed on October 2018.
(*) Export Credit Agency
2021
The new Line 3 is
expected to start
operating during the
fourth quarter 2021,
while Line 1 is
shutdown.