Investor Presentaiton slide image

Investor Presentaiton

MAPA PROJECT TIMELINE July 2018 The Board of Directors approved the MAPA Project. February 2019 Earth-moving works start. May 2019 Contracts awarded for construction companies, totaling approximately US$ 680 million. End of July 2021: 86% progress Main equipment and parts on-site and construction continues. April 2011 Arauco's first environmental studies for MAPA Project. October 2018 Arauco signed main equipment contracts with Andritz and Valmet April 2019 On April 1st, 2019, Arauco signed an ECA* agreement for a total of Eur 555 million. This financing is mainly associated with the suppliers contracts signed on October 2018. (*) Export Credit Agency 2021 The new Line 3 is expected to start operating during the fourth quarter 2021, while Line 1 is shutdown. arauco carbon neutral 25