Investor Presentaiton

The FIT Determination Process Proposals Received initial proposal from each RE association Consultation and Evaluation In accordance with the ERC FIT Rules Obtained comments from third party consultants of the DOE ➤ Applied uniform financial model for all technologies ➤NREB conducted consultation and verification as follows: Met with developers from January 2009 to April 2011 • Verified the figures from project submissions by developers to the DOE • Verified from actual cases and decisions by the ERC ➤ Applied international and historical benchmarking on project costs, O&M, and technical assumptions Recommendations In conformity with ERC Rules of Practice & Procedure on Rule- making. ➤ Representative project ➤Single rate for each technology initially. Differentiated FITS per technology to be submitted as a supplement to the initial Petition ➤ FIT Application with ERC was submitted on 16 May 2011