IIIII
National & cross-national ambition setting
42 countries now have a hydrogen strategy (up from 3 in
2019). The total electrolyser target across these hydrogen
strategies is approx. 90 GW by 2030. An additional 36
markets are preparing a hydrogen strategy.
Ørsted Power-to-X highlights during Q1 2023
Project development
Ørsted Power-to-X continues to mature a
pipeline of renewable hydrogen and e-fuels
projects, primarily building on a foundation of
project opportunities in Northern Europe and
North America.
Substantial progress in visibility of push and pull policies
Critical regulatory success has been achieved in the EU by
getting visibility on the definition of renewable hydrogen and
with the introduction of binding targets for hydrogen in industry
and transport, mandates for e-fuels in shipping and aviation,
and by opening up new direct funding instruments.
Project announcements & increasing demand
Global announced projects indicate significant build-
out ambitions of c.290 GW electrolyser capacity
toward 2030. Evidence of growing offtake e-fuel
demand includes c.110 methanol vessels on order or
operating (up from c.80 at the end of 2022).
Scalable hubs
Ørsted Power-to-X is pursuing synergies from
co-locating projects- for example, the
SeaH2Land project portfolio in the
Netherlands and exploring scaled project
phasing at Idomlund in Denmark.
FlagshipONE maturation
Ørsted's board of directors approved the
50,000 tpa e-methanol Swedish project in
December 2022. Construction will start in
May 2023 and COD is expected in 2025.
Source: BNEF Global Hydrogen Strategy Tracker, S&P/IHS Markit, DNV Alternative Fuels Insight