Green Hydrogen Work Progress Update

• • Peachtree Green Hydrogen Plant - Camden County, Georgia Jul 2022 15 TPD LH2 (Future expansion to 30 TPD underway) Grid connected In-person sales showcase: product portfolio in action, customer training, construction details and planning Design optimization and EPC benefit for other plants Construction timeline of about 12 months vs. industry standard of 36-48 months plug Sep 2022 Dec 2022 May 2023 Night shift Mar 2023 Cooling Towers Grid Substation 8