KPCL 110 MW
Barge Mounted Plant
(KPCL-I)
(Asset held for sale)
1st Extended PPA Contract:
The 1st extended 5 years term PPA
with Bangladesh Power Development
Board (BPDB) expired on 12 October
2018. However, the extension of KPCL
20 year's old plant is under discussion.
Generating Plant:
19 X Wärtsilä 18V32 DG Sets
Location:
Goalpara, Khalishpur, Khulna
Capacity:
110 MW Barge mounted power plant
Description of Barges:
Two floating barges named Tiger I
and Tiger - III. Nine generating units
are mounted on one barge and ten
on the other. The barges shipped
as deck cargo on submersible
dry tow ship, are moored in a
closed basin. Each barge is
approximately 91 metres long
and 24 metres wide.
Fuel used:
Runs on Heavy Fuel Oil (HFO), however,
having duel fired capability and can be
converted into natural gas operation.
Project Cost:
USD 96.07 million