Investor Presentaiton
Illustrative Timeline to First Lithium¹
Year -1
Year O
Year 1
Year 2
LAKE
RESOURCES
Year 3
Months
1
2
3
4
5
6
7
8
9
10 11 12 13
14
15
16 17 18 19 20 21 22
23 24 25 26
27
28 29
30 31
32 33 34 35
36 37
38
39 40
41 42 43
44 45
46 47 48
Corporate
Operations
Pre-FID
Equity Raise¹
Strategic partner process (JV)²
ECA debt raise process²
EIA Approvals²
EPCM & Power FEED(s)²
FID
•
Strategic Partnering (JV) Process: Completion anticipated Q3 - Q4 2024
●
Post-FID
First
Production
Construction & Commissioning²
EPCM and Power FEED: Completion anticipated 9 – 12 months after Strategic Partnering Process
Final Investment Decision (FID): 9 - 12 months after completion of Strategic Partnering process
First Lithium: 30 months after FID
1 Refer to ASX announcement dated March 4, 2024. 2 Timing is indicative only and subject to change. This timeline has been prepared solely on the basis of information that has been released to the market and no other information.