Investor Presentaiton
1. Outline of Japan Airport Terminal Group
(8) Changes in Capital Investment
Fisical Year
Details
Investment (at time
of construction)
1955
Construction of former terminal building
1963
Major expansion and renovation (Measures for jet aircraft and the Olympics)
1970
1977
1978-1981
Construction for accommodating jumbo jets (domestic and international terminal buildings)
Construction for disaster safety measures
Construction to repurpose domestic terminal accompanying shift to international flights at Narita
Airport
Construction for domestic terminal redeployment
Construction to build Terminal 1 building and remove old terminal building
Terminal 1 building renovation (bus lounge expansion, new boarding stations)
Construction to build provisional international terminal building
Renovation of Terminal 1 building (barrier-free measures)
1984
1993
1997
1998
1999 2002
2002
2004
Expansion and renovation of provisional international terminal building
Construction to build Terminal 2 building
2004 2005
2006
2007
Renovation of Terminal 1 building (including marketplace revitalization)
Provisional international terminal building expansion and renovation
Construction for expansion of Terminal 2 building (Second Stage of the Plan)
Construction to build P4 simplified parking structure
2007~2008
Provisional international terminal building expansion and renovation
Construction of Terminal 3 building and P5 parking [TIAT]
2008~2010
Terminal 2 building expansion (Third Stage of the Plan)
Construction to convert P4 parking lot to multi-story parking lot
¥1.0 billion
¥3.5 billion
¥3.2 billion
¥8.0 billion
¥11.5 billion
¥15.0 billion
¥136.0 billion
¥2.0 billion
¥1.5 billion
¥3.4 billion
¥1.0 billion
¥67.0 billion
¥15.0 billion
¥0.6 billion
¥11.5 billion
¥2.0 billion
2011
2012 2014
2013
2017~2019
Terminal 1 building renovation (departure lobby, departure lounge, observation deck, etc.)
Terminal 3 building expansion (expansion in 8 spots, lobby expansion, etc.) [TIAT]
Terminal 2 building expansion (Fourth Stage of the Plan) Expansion in 3 spots
2018-2019
Terminal 2 building expansion (international flight facility, satellite, office space expansion, etc.)
Terminal 3 building expansion (expansion in 2 spots, lobby expansion, etc.) [TIAT]
Terminal 1 building renovation (basement, 1st floor arrival lobby interior modification, etc.)
¥3.6 billion
¥100.0 billion
¥19.0 billion
¥6.0 billion
¥7.0 billion
¥70.0 billion
¥7.6 billion
¥74.0 billion
¥21.0 billion
¥4.7 billion
Total ¥595.1 billion