G
NEA
Nuclear Energy Agency
All ABWR NPPs in Japan
OECD
Plant
Construction
Commercial
Start*
Operation
7 ABWRs
●Hokuriku Electric Power Company
Shika 2
⚫EPDC
Ohma
Kashiwazaki- Nov. 1992
Nov. 1996
Kariwa 6
Kashiwazaki- July 1993
July 1997
Kariwa 7
The Chugoku Electric Power Company
Shimane 3
◆Tokyo Electric Power Company
Higashidori 1
Hamaoka 5
July 2000
Jan. 2005
Shika 2
Aug. 2001
Mar. 2006
Tokyo Electric Power Company
Kashiwazaki-Kariwa 6,7
Shimane 3
Sep. 2007
defered,
TBD
Chubu Electric Power Company
Hamaoka 5
Ohma 1
Hagashidori
May 2010
TBD
defered
(*: Construction Start is based on the first concrete of
the reactor building base mat)
OECD NEA Workshop on Project and Logistics Management, Paris, 11th March 2014