Northland Power Capitalized Growth & Strategic Overview

European Offshore Wind Facility Details Gemini 600 MW Capacity Distance to Shore Wind Turbines Turbine Foundation Water Depth Total Project Costs Revenue Contract Type Revenue Contract Term 85km 150 x Siemens 4 MW Monopile 28m to 36m €2.8 Billion Contract for Differences (CFD) (FIT-Type) 15 years Nordsee One 332 MW 40km 54 Senvion x 6.15 MW Monopile 26m to 29m €1.2 Billion Feed in tariff ~ 10 years €194/MWh for 8 years, €154/MWh for 1.5 years [No escalation] Deutsche Bucht 0 NORTHLAND POWER 252 MW 95km 31 x MHI Vestas 8MW Monopile 39m to 41m €1.5 Billion Feed in tariff ~13 years €184/MWh for 8 years, ~€169/MWh Revenue Contract Price [No escalation] €149/MWh for 4.7 years [No escalation] Grid Connection Responsibility Gemini responsible for connection to shore Tennet responsible for connection to Tennet responsible for connection to shore shore NPI Ownership 60% 85% 100% Northland Power | 44