The Africa Challenge – Khemisset Potash Project slide image

The Africa Challenge – Khemisset Potash Project

THE GEOLOGY AND LOCATION ARE UNIQUE ADVANTAGES Low infrastructure costs 2 declines. Easy mine access Low risk Total CAPEX Construction Time Location AISC Total Transportation Cost FOB Shipping TYPICAL CANADIAN PROJECT KHEMISSET PROJECT AA 昼昼 No aquifer 135Km 500m Highway already established Declines $35m Mining costs Shafts $1.1bn High infrastructure costs 2 deep shafts through aquifer. High risk £ 1 Aquifer ~1,000m No port development Shipping to Brazil costs $12.6m Infrastructure $200m $0 ง Port $150m High port development Shipping to Brazil costs 1,700Km Rail connection to port $29/t incl. royalties Logistics Cost $145/t Khemisset Project US$411m 2 years to completion 135km from Port of Casablanca US$158/tonne US$29/t BHP Jansen Project (Canada) US$5.7bn 6 years + 2 years ramp up 1,800km from Vancouver US$115/t US$145/t US$14/t US$15/t US$70/t US$75/t 10 10