Expansion Projects Completed & Ongoing
-
MRS. BECTOR'S
CREMICA
1 Biscuit Line
at Rajpura (Punjab)
The Company has invested on another Biscuit line from the IPO Proceeds of Rs. 40.5 crores to finance the cost
of Rajpura Expansion Project. The commercial production has started in month of May 22.
ENGLISH
Ⓡ
OVEN
Shifting of 2 Biscuit Lines
from Tahliwal (HP) to
Rajpura (Punjab)
Biscuit Line at Dhar (MP)
.
2 Biscuits Lines proposed to be shifted from Tahliwal to Rajpura due to high transport and labour cost. Total
Estimated cost is Rs. 50 crores. Total projected savings is Rs. 10 crores per year on account of Labour, Power,
Fuel, Indirect wages and transport cost. Estimated time lines of completion is Dec 22
The Company is planning to start construction work this year for manufacturing line of biscuits.
It will take 12-15 months and shall commence production in FY23-24
Expansion of Bakery Plant
in Khopoli (Maharashtra)
Bread and bakery Plant in
Noida and Punjab
•
Company has purchased land in Khopoli, Mumbai adjacent to our factory for expansion of our Bakery business.
Total Project is Rs. 73 crores including Land out of which Rs. 25 crores will be invested in FY23 and balance in
FY24. Commercial Production proposed to be started in Oct 23.
The Company has invested Rs. 62 crores on additional line of Bread and a Bun line at Greater Noida factory.
Both these lines have become operational since October 2021,
The company planning to invest Rs. 20 crores in Punjab for manufacturing of bread and bakery items.