Corentyne Acreage and Activity Overview slide image

Corentyne Acreage and Activity Overview

Power to Port www.cgxenergy.com cgx energy inc Contract Summary Component Name: Power to Port Progress: 100% completed Timeline: 16th October 2020 to 15th December 2021 Contractor: Guyana Power and Light Inc. Specifications -70 KVA transformer - Installed by GPL - 3-phase capacity with stepdown to 110/220 2-phase 31