CEZ Group Energy Transformation and Financial Results
NEW NUCLEAR PROJECT IS IN THE FIRST PREPARATORY
STAGE THAT IS COVERED BY THE SIGNED FIRST
IMPLEMENTATION CONTRACT...
ப
G
A
Framework contract
End
Stage
date
Expected
costs*
(EUR billion)
Permitting and licensing
Contract with technology supplier
B
First implementation contract
Power Purchase Agreement (TBD)
C
Repayable Financial Assistance (TBD)
A
1. Preparation,
ΕΙΑ
B
Investor Agreement (TBD)
supplier
2024
~0.2**
selection
Site decision
License for the siting
Tender process and contract signature
2. Preliminary
works
2029
~0.7
License for construction,
Building permit
"LWA - Limited Work Authorization"
phase
3. Construction,
2036
commissioning
~5.1
License for
commencement of trial
operation
Construction
4. Warranty
period
2038
*
At 2020 prices, rounded
**
Operation license
Warranty period operation
It does not include the costs incurred until 2020 for the permitting and contracting and the purchase of land; assuming the current supplier model