Fountain Head and Hayes Creek Project Development
Plant and Infrastructure
Mitigation of capital cost pressures
Capital cost estimates updated by
Como -20% increase
Initiatives employed to offset and
remain in-line with the PFS estimate
of A$46m, include;
2nd hand equipment; suitable
tailing filtration equipment
assessment underway
Modular Plant design; reduce
time
and
site-based
construction costs
Mobile crushing plant; chosen
over fixed units to achieve
greater flexibility and ease of
financing
Option for stand-alone hybrid
power station positive, up to 41%
renewable power reduces overall
carbon footprint and unit operating
costs
Tailings Filtration system including filter press (background) and thickener (foreground) that PNX is
assessing for use at the Fountain Head project. The equipment would be transported and
reconstructed at Fountain Head