5. Addressing Reform in the Power Sector
5.2 Allocation for Ruppur should be reduced
•
Ruppur Nuclear Power Plant received the highest allocation in the ADP
(Tk.18426 cr.) which will help the project to complete 53% of the project
Given the huge amount of access electricity in hand, such huge allocation
for quick implementation of the project (target 2025) would create a
pressure for surplus electricity
Allocation for the project should be reduced - both from the government
and from the Russian government
The extracted allocation should be used for RE based power generation
Allocation for Ruppur nuclear power plant and its transmission activities in FY22
Name of project
Implementing
organisation
Type of Allocation
Project
FY22
Project Aid
GOB
Maximum
Possible
Completion
by FY22
Project
completion
status
Ruppur nuclear power plant
Bangladesh
Nuclear Energy
Generation
1842616
1600000
242616
53%
Continuing
Commission
Development of transmission
infrastructure for generated
power evacuation of Ruppur
Nuclear Power Plant
PGCB
Transmissi
on
207939
164995
42944
24%
Continuing
Total
2050555
1764995
285560
36View entire presentation