Sembehun Project Feasibility and Market Dynamics slide image

Sembehun Project Feasibility and Market Dynamics

Phase 2 Indicative Timeline PFS Complete 2022 Sierra Rutile Limited Sierra Rutile's approach is expected to see the development of Sembehun integrated with the remaining operations at Area 1. The below timeline is based on the recently completed Sembehun PFS Phase 1 Project Assessment DFS Final Investment Decision 2023 2024 2025 2026 2027 2028+ Detail Engineering & Procurement Phase 1 Construction Phase 1 Commissioning Procurement Ramp-Up Steady state production Note: Sierra Rutile is working towards being in a position to make a final investment decision in 2023 which would allow Sierra Rutile to target the commencement of Phase 1 Sembehun production within 24 months. This timeline is indicative and may be subject to change including due to matters outside Sierra Rutile's control. Refer to Appendix H for information on key risks. Phase 2 Construction Phase 2 Commissioning Ramp-Up Steady State Production 223 23