Business Strategy Execution
Out of the 20 GW of 2021-25 capacity additions, EDP has 40% already
installed or under construction and 55% secured
EDP continues to accelerate growth across all
platforms, with +3.7 GW installed & U/C YTD
10.8 GW committed capacity vs. growth target 2021-25
40%
of the 20 GW capacity
additions target
20 GW
Short-term challenges have implied some
transfers from 2022 to 2023...
ā
Supply chain delays and regulatory uncertainty in US
implied the postponement of some capacity
additions from 2022 to 2023, expecting additions of
>2 GW in '22
>4.0 GW to be added in 2023 of which ~3.0 GW are
already under construction
edp
8.1 GW
2.7 GW
55%
... but we are also seeing many long term
opportunities in the market
BP
7 Growth prospects for 2024-25 and beyond to be
supported by Repower EU and Inflation Reduction Act in US
Installed & Under
construction
Secured
to be added
2021-25
Business Strategy Execution