Investor Presentaiton
KEFI
GOLD + COPPER
Jibal Qutman
-Development Schedule
when Mining Licence Lodged in 2016
Infill Drilling and Final Resource Jan 1 - Jun 1
Environmental Studies and Permits
Optimise Metallurgy and Mine Plan
Jan 1 Jul 15
Definitive Feasibility Study (Reserve)
Financing
Jan
Apr
Jul
Oct
Dec 1 Dec 31
Jun 1 - Mar 4
•
gold
& minerals
Mine Metrics
Mining 1 Mtpa
Production 20k oz pa
•
Average Op Cost c. US$600/oz
•
Initial capital US$38M
Jan 1 - Jun 30
FEED and Long Lead Orders
Dec 2 - Sep 2
Construction Plant and Infrastructure
Jan 1 Oct 30
Mining and Stacking Leach Pads
Final Investment Decision
Dec 29
2017
Apr
Jul
Oct
First Gold Bar
Jan 2
Nov 1 Mar 6
2018
2018
Mining Licence Application submitted in Dec 2016 based on Dec 2015 Sedgmen scoping study.View entire presentation