KEFI GOLD + COPPER Jibal Qutman -Development Schedule when Mining Licence Lodged in 2016 Infill Drilling and Final Resource Jan 1 - Jun 1 Environmental Studies and Permits Optimise Metallurgy and Mine Plan Jan 1 Jul 15 Definitive Feasibility Study (Reserve) Financing Jan Apr Jul Oct Dec 1 Dec 31 Jun 1 - Mar 4 • gold & minerals Mine Metrics Mining 1 Mtpa Production 20k oz pa • Average Op Cost c. US$600/oz • Initial capital US$38M Jan 1 - Jun 30 FEED and Long Lead Orders Dec 2 - Sep 2 Construction Plant and Infrastructure Jan 1 Oct 30 Mining and Stacking Leach Pads Final Investment Decision Dec 29 2017 Apr Jul Oct First Gold Bar Jan 2 Nov 1 Mar 6 2018 2018 Mining Licence Application submitted in Dec 2016 based on Dec 2015 Sedgmen scoping study.