Airport and Energy Business Overview
Key Developments in Q4FY21-Airport Business
GAR
Goa Airport
.
Work is in progress at site with physical activities being carried out simultaneously at multiple sites
of the project including Runway, Earthwork, ATC etc.
Achieved Milestone III in terms of both financial and physical progress within the agreed timelines
as defined in Concession Agreement and have achieved physical progress of 28.26% as of March
31, 2021. As on May 31, 2021, the project has achieved a progress of 33.1%.
Land acquisition for the expressway (NH166S) connecting NH 66 to MOPA Airport is nearing
completion & expressway is expected to be operational by COD of the airport.
Crete Airport
Earthworks are progressing in multiple fronts of runway, taxiway, apron, terminal building, external
access roads
~3.6% financial progress is achieved with completion of ~10% of earthworks in airport area and
~9.8% of earthworks in access roads as of March 31, 2021
As on May 31, 2021, ~4.8% financial progress is achieved with completion of ~22% of earthworks
in airport area and 15% of earthworks in access roads
Bhogapuram Airport
Land acquisition and R&R works in progress; Preliminary works and design in progress