Investor Presentaiton
N
NRA, Japan
Nuclear Regulation Authority
Contaminated Water Remaining
in Trenches
■ Highly contaminated water remains in the main trenches in
seaside area. Contaminated water is flowing in from T/Bs.
■ TEPCO attempts to drain the water after plugging the flow
paths by using the similar technique to that to be used for frozen
ice wall.
Shaft B
Tunnel A
Planned freezing point
Ice plugging
3
2
O.P.+10m
Trench B
Shaft C
Trench C
Tunnel B
Tunnel B
Unit 2 seawater pipe
trench
Shaft A
Freezing operation
since April 27
Shaft D
Mobile treatment
equipment
Tunnel A
Unit 3 seawater pipe
trench
Trench A
Trench D
Turbine Building
Shaft
Cable
tray
Grouting
OP+7.4m
Water level
O.P. +3m
Shaft
T/B Unit-2
Freezing operation
since June 13
Drilling in progress
T/B Unit-3
Main trenches and ice plugging operation
Source TEPCO, edited by the author:
http://www.tepco.co.jp/en/nu/fukushima-np/roadmap/images/d140627_01-e.pdf
duct
3
Tunnel
2
Schematic of main trench at Unit 2
Source TEPCO, edited by the author:
http://www.tepco.co.jp/nu/fukushima-np/roadmap/images/t130627_11-j.pdf