Investor Update
Projected Tsimiroro Block 3104 Work Schedule
2010 Actual Schedule
2011 Estimated Schedule
2012 Estimated Schedule
2013 Estimated Schedule
JFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJ
Rainy Season
Rainy Season
Rainy Season
MADAGASCAR OIL
2014 Est. Schedule
A S O N D J F M A M J J
Rainy Season
Block 3104
Structural Interpretation
Rain
ERT contracting
ERT mobilization
ERT acquisition
ERT lab processing
Reservoir analysis
NSAI Study
Delineation drilling
Mobilization
Drilling
Steam Flood Pilot
Engineering and Design
Site Preparation
Permitting
Infrastructure improvements
Rebuild Steam Generation Equip.
Drilling equipment
Drill and complete 28 wells
Install Steam Generation Equip.
Staffing and supervision
Long lead items - Facilities
Central plant construction
Field piping
Electrical
System Testing
Water source and disposal
Pre-Commission Systems
Start cyclic steaming
Start continious injection
Production test
Steam Flood evaluation
17 June 2011
Delay time
Work completed
Projected work
Projected work-partial progress
Investor Update