MARITIME LINK – ON TIME ON BUDGET Construction Activities in 2015 Completed road at Indian Head Access Road to Big Lorraine Point Aconi Cable Transition Compound Major Contracts Awarded – 93% of Total Contracts Committed Abengoa awarded transmission construction contract Nexans awarded subsea cable contract ABB awarded converter contract Spend to Date* 32% 21 Emera 21 *Total spend as a percentage of total project budget as of September 30,2015