Australia Coal and Laos Power: Operational and Financial Summary
BANPU
Mongolia coal: project developments
TSANT UUL PROJECT
OVEN PLANT INSTALLATION
■
Plant installation completed and obtained.
government inspection approval.
■ Performed a series of test runs and
obtained 5,000 liters of tar oil products.
■ Preparing technical pre-feasibility study
and market study for commercial-scale
project.
UNST KHUDAG AND ALTAI NUURS PROJECTS
Unst Khudag Project
◉
◉
Completed updated geological and
mining models
Continuing water resource modeling and
development
Currently conducting preliminary
feasibility program for coal conversion
and power facility scenarios including
technical and market related studies
Altai Nuurs Project
■
■
Completed hydrology and baseline
environmental studies
Obtained preliminary mining agreement
approvals from the Mongolian
Government
26View entire presentation