New York Onshore Wind Project Overview
Acquired three New York onshore wind development projects in 2020. Projects
expand Northland's North American portfolio by providing investment
opportunities into the US renewables market
Well positioned from a competitive standpoint relative to the state's wind
development pipeline
USD cash flows from stable and high demand market
320 MW potential capacity (Bluestone, High Bridge and Ball Hill)
Secured 20-year indexed REC contract (CfD all-in PPA) with with the New York State
Energy Research and Development Authority
Achieved financial close on Ball Hill and Bluestone in Q2 2021 and actively
developing Highbridge
Timeline For NY Wind Development
2021
2021
2022/23
Acquired Projects
Secured 20 year
28
IRec Offtake
Expect to start
Construction
Expected
Commercial
NORTHLAND
Operations