PTTEP Project and Financial Overview
Projects Details | Thailand
PTTEP
Project Name
Status
Phase
Participating Interest* (%)
Sales Vol Gas
(MMSCFD)
Sales Vol Liquid
(KBPD)
Latest Status
15
MTJDA
JOC
Production
260
10
PTTEP
50%
Facility Readiness for Additional Gas to DP1 (Thailand) for 30-50 MMSCFD
Petronas Carigali
50%
16
G9/43
OP
Exploration
PTTEP
100%
Activity suspended
17
G1/61 (Erawan)
OP
Exploration
PTTEP
60%
Mubadala
40%
18
G2/61 (Bongkot)
OP
Exploration
PTTEP
100%
PTTEP denotes respective PTTEP subsidiaries participating in the project
Note: *
**
Sales volume represent average volume for 100% of the project during Q1/2022
***
Status: OP PTTEP operatorship/JOC = PTTEP joint operatorship/ JV = PTTEP Joint Venture Partner
36
96
Awarded as an operator for Erawan field (Contract 1, 2 and 3) under PSC
(after concession-end in 2022)
Preparing all transitional works including platform site survey under Site
Access Agreement#2, construction of facilities, staff recruitment, and
related procurement activities, aiming for successful transition and gas
production as per commitment.
Signed Gas, Crude and Condensate Sale agreements
Awarded as a sole operator under PSC (after concession-end in
2022/2023)
Signed Gas and Condensate Sale agreements
Continue drilling development wellsView entire presentation