NECESSARY PERMISSIONS FOR BUILDING AND LAUNCHING FACTORY alabuga Type of work Design according to Russian standards State examination Construction permit Building development Installation and commissioning of the equipment Statement of conformity of design documentation and technical rules Permission to launch Total: The timeline 6-9 months 2-3 months 2 weeks 1-1.5 years 6-9 months (in parallel with construction) 2 months 2 weeks 2-3 years