Fresnillo Results Presentation Deck
2021 PRELIMINARY RESULTS - PROJECTS
STRONG PROJECTS FOR THE FUTURE - ORISYVO, RODEO & GUANAJUATO
ORISYVO (GOLD)
●
●
●
●
In 2021, we concluded a detailed metallurgical
investigation, confirming good recoveries in the oxide
zone and improving recovery rates in the sulphides.
70% progress in geotechnical drill programme
Conceptual mining and ore processing scenarios in
study. Prefeasibility study scheduled to be completed
in 2023
Baseline environmental, social, energy, hydrological
studies, amongst others, are on-going
Expected avg. annual gold production: 140-165 koz
Resource: 9.6 moz Au (based on an open pit shell)
RODEO (GOLD)
In 2021, we refined the preliminary economic
assessments. Detailed metallurgical investigation,
infrastructure and hydrological studies are on-going
●
●
●
Strengthened a region-wide community relations
programme
In 2022, we aim to reach agreements with local
communities regarding access to land
Expected avg. annual gold production: 130-150 koz
Resources of 1.3 moz Au, 13.8 moz Ag
GUANAJUATO (SILVER / GOLD)
●
●
●
●
20
49,047 metres of core drilling was completed in 2021
Both the total and the indicated resources have increased
and are approaching a critical mass which will be best
evaluated in an updated PEA expected to be completed in
2023
Central Zone Resources of 1,013 koz Au, 37.9 moz Ag
North Zone Resources of 437 koz Au, 19.7 moz Ag
South Zone - Resources of 243 koz Au, 43.0 moz AgView entire presentation