NHPC Capacity Addition and Financial Overview

NHPC -Projects Under Survey & Investigation E S. No. Projects Installed State Capacity (MW) Projects Under FR/DPR Preparation 2 Dulhasti Stage-II UT of Jammu & (2x130) Kashmir 260 Total 890 Status 36 एनएचपीसी NHPC MOU has been signed between NHPC Ltd. and JKSPDCL on 03.01.2021. The project shall be executed by NHPC on BOOT basis for the period of 40 years. 1st Consultation Meeting with CEA for preparation of DPR was held on 17.03.2021 and Minutes of Meeting (MOM) was issued on 25.03.2021. MOEF&CC vide letter dated 16.07.2021 has conveyed the approval to the TOR for EIA/ EMP studies of the project. EIA studies are in progress. No forest clearance is required. NOC has been obtained from Forest department. Defence Clearance has been accorded by MoD on 03.01.2022. All (9 nos.) Pre-DPR chapters have been submitted to concerned directorates of CEA/CWC/GSI/CSMRS etc. and 7 Chapters cleared out of 9 Chapters.