POLYMETAL INTERNATIONAL PLC POX-2 Key project milestones INVESTOR PRESENTATION 40 Q2 2019 Q1 2020 Q3 2020 Q3 2021 Q1 2022 Start of detailed engineering and construction Receipt of all permits Delivery of the autoclave on-site Completion of civil construction works Completion of main equipment installation Completion of external infrastructure Mechanical completion and start of commissioning activities Q3 2022 Q4 2022 Q3 2023 Q4 2023 Full ramp-up End of commissioning and first production