Projects under Construction
EXTENSION /
LOCATION
PARTNERSHIP
CONCESSION
START
PREVIOUS INSTALLATION
LICENSE
LICENSE
ANEEL
DEADLINE
82 km
Mariana
100% Taesa
Minas Gerais
May
2014
✓
May/16
√
Dec/18
(1)
December
2019
Miracema
90 km
Tocantins
100% Taesa
June
✓ Oct/17
✓
Apr/18
December
2019
SUDAM
tax benefit
2016
25% Taesa
EDTE³
168 km
Bahia
50% ENTE
December
2016
✓ Jun/18
December
2019
Jan/19
25% Apollo 12
236 km
50% Taesa
ESTE
Minas Gerais and
Espírito Santo
50% Alupar
(100% EATE-TBE)
February
2017
✓
Jan/19
February
2022
Janaúba
542 km
Bahia and Minas
100% Taesa
February
2017
✓
Sep/18
Gerais
Aimorés
208 km
Minas Gerais
50% Taesa
50% ISA Cteep
February
2017
✓
Oct/18
Paraguaçu
338 km
Bahia and Minas
Gerais
50% Taesa
50% ISA Cteep
February
2017
✓ Oct/18
Ivaí
600 km
Paraná
50% Taesa
50% ISA Cteep
August
2017
✓ Apr/19
✓
✓
Jul/19
Apr/19
✓ May/19
(2)
February
2022
February
2022
February
2022
August
2022
SUDENE
tax benefit
SUDENE
tax benefit
SUDENE
tax benefit
Sant'Ana
591 km
Rio Grande do
Sul
March
100% Taesa
2019
(1) Conclusion time estimated by the Company