Minas-Rio Impairment Considerations and Project Delivery slide image

Minas-Rio Impairment Considerations and Project Delivery

BENEFICIATION PLANT Current status and points of attention Key stats 53% complete 92% of beneficiation plant earthworks completed 43 of 187 transmission line towers released for construction 79,000 m³ of concrete poured to date ~4,000 people at site LICENSING LAND ACCESS ■ Continuous focus on government relations ■ Active engagement and follow-up with forestry, environmental and archaeological agencies ■ Conclude land access for transmission line towers ■ Strategic plan for future land requirements ■ Monitor escalation factors in the construction industry ■ Focus on top contractors PROCUREMENT 15 15