Whole Life Value Optimization of Boral Quarries
Cement - Geelong position and project update
-
Our Geelong Cement Facility total project investment of $165m is delivering cost and customer benefits
The Geelong Cement Facility was commissioned in H2 2022
at a total cost of $165m very close to on time
The facility has capacity for 1.7m tonnes per annum of grey
equivalent cement
The portside facility allows for conveyor unloading from ship
to clinker store to mill
ā
The facility will imports clinker and slag for milling
The operation includes two ball mills and a slag dryer; raw
material storage of multiple clinker sources; four finished
product silos with two despatch lanes
The new capacity and the addition of slag supply will support
planned growth in volumes, future market growth and
support the broader cement network with options to reach
into SA and Tasmania