IFI Sales and Performance Projection slide image

IFI Sales and Performance Projection

MAIN SUPPLIERS AND CONTRACTORS (UPDATE AS OF NOV 2021) SUPPLIERS/ CONTRACTORS NO 1 Yalian Machinery Co. Ltd 2 Shandong Huatai Power Eng. 3 Others SCOPE OF SUPPLY/WORK MDF Line Machine 1st Delivery in February 2022 2nd Delivery in March 2022 3rd Delivery in May 2022 Finish installation in Q1 - 2023 Power Plant including steel structure 1st Delivery in March 2022 2nd Delivery in May 2022 Finish installation in Q1 - 2023 Pre Project, Land Cut and Fill, Pilling, Building, Installation, Houshing, etc CONTRACT VALUE IN FOREIGN CURRENCY RMB 100.000.000 RMB 57.000.000 CONTRACT VALUE IN RUPIAH CURRENCY Rp. 154 Billion Note: The contract/PO above is the realization of the progress of construction planning until November 2021 and will increase along with the final completion of the construction plan. 29 IFI