IFI Sales and Performance Projection
MAIN SUPPLIERS AND CONTRACTORS (UPDATE AS OF NOV 2021)
SUPPLIERS/
CONTRACTORS
NO
1
Yalian Machinery Co. Ltd
2
Shandong Huatai Power Eng.
3
Others
SCOPE OF SUPPLY/WORK
MDF Line Machine
1st Delivery in February 2022
2nd Delivery in March 2022
3rd Delivery in May 2022
Finish installation in Q1 -
2023
Power Plant including steel
structure
1st Delivery in March 2022
2nd Delivery in May 2022
Finish installation in Q1 -
2023
Pre Project, Land Cut and Fill,
Pilling, Building, Installation,
Houshing, etc
CONTRACT VALUE
IN FOREIGN
CURRENCY
RMB 100.000.000
RMB 57.000.000
CONTRACT VALUE
IN RUPIAH
CURRENCY
Rp. 154 Billion
Note: The contract/PO above is the realization of the progress of construction planning until November 2021 and
will increase along with the final completion of the construction plan.