RESERVE & RESOURCE UPGRADES
PROJECT MILESTONES
Yangibana Milestones since 2014
First exploration to construction start
Nov 17
Native Title
agreement
signed
Nov 17
DFS
completed
2014
2015
2017
2018
Sep 14
6.8 MT JORC
Resource
Nov 15
12.4 MT JORC
Resource
Oct 17
20.7 MT
JORC
Resource
Hastings Technology Metals Limited (HAS.ASX)
Nov 17
5.2 MT JORC
Reserves
Feb 19
Successful 2nd pilot
-
plant test Higher
yield
Nov 18
Skyrock Baotou
offtake contract
signed
Nov 18
Total Resource
increased to
21.7MT
2019
Feb 19
JORC Reserves
increased to
10.35MT
Oct 19
EPCM contract
signed with DRA
Global
Aug 19
WA Minister of
Environment
Approval
obtained
Investor Presentation, 25 November 2021
Jun 20
Schaeffler
Master Supply
Agreement signed
Apr 20
Commonwealth
Environmental
Approval
2020
Jul 20
Finnvera In Principle
ECA Eligibility
July 20
Bene & Hydromet
Plants Decoupled
Feb 21
$100M
Equity
Raised
April 21
TK Offtake
Contract
signed
70,000t
2021
HASTINGS
Technology Metals Limited
Aug 21
Earthworks
Construction
Start
Nov 20
8km long
Mineralisation
confirmed at
BH-SF-F
July 21
16.7MT Reserve
15 Year LOM
May 21
27MT JORC
Resource