NHPC Financial Highlights & Renewable Energy Projects
NHPC Standalone Projects Under Clearance
S.
Installed Design
Projects Capacity Energy
Cost
(In Crore)
N.
(MW)
(MUs)
1 Teesta-IV
520
2252
(4x130)
Sikkim
& PL
6113
(Apr'21)
•
•
.
2
Dibang
(12x240)
2880
11223
Ar.
Pradesh
31876.39
(May'21)
•
Status
एनएचपीसी
NHPC
•
•
•
.
•
All statutory clearances have been received except forest clearance (stage-II).
Compliance to FRA, 2006 is in progress.
Approval for pre-investment activities received on 03.05.2016.
PIB memo incorporating comments of appraising departments submitted to MoP on 08.04.2022.
Hon'ble Minister of Power and Minister of New & Renewable Energy, Govt of India vide DO letter
dt 09.05.2022 requested Chief Minister of Sikkim for expeditiously resolving the pending issue of
FRA compliance & private land acquisition.
Gram Sabha meeting for Lum-Gor-Sangtok GPU was held on 08.10.2022. Final outcome report is
awaited from District administration.
Hon'ble Chief Minister, Sikkim held a meeting on 28.10.2022 along with Chief Secretary, Addl.
PCCF from State Govt. with CMD, NHPC & other senior officers, in connection with
implementation of Teesta-IV HE Project in Sikkim. Hon'ble Chief Minister assured all support from
Govt. of Sikkim for early implementation of the Project. CMD, NHPC vide DO letter dated
22.12.2022 has appraised the Secretary, Ministry of Power about the issues related to the project.
Regular persuasion is being done with State Government for expeditiously resolving the issues of
compliance of Forest Clearance (Stage-II) related to FRA, 2006 and acquisition of 181.06 ha
private & departmental land.
Concurrence to Project, Environment Clearance, Forest Clearance (Stage-1) and Forest
Clearance (Stage-II) have been received.
CCEA approval for Rs. 1600 crore to incur expenditure on pre-investment activities & balance
clearances of the project has been accorded.
PIB in its meeting held on 11.10.2022 recommended the proposal regarding implementation of
the Project by NHPC Ltd. for consideration of CCEA. Minutes of meeting issued on 28.10.2022.
Draft material for CCEA note submitted to MOP on 28.10.2022. Draft CCEA note stands concurred
by MoF vide OM dated 29.11.2022. As sought by PMO / MOP, requisite inputs / information were
provided from time to time. Presently, CCEA note is under advanced stage of finalization /
approval.View entire presentation