Teles Pires 1,820 MW Waiting the Mauá 3 590 MW Nov-17 conclusion of the TL Santo Antônio 3,568 MW 2,286 MW under operation Jirau 3,750 MW 2,400 MW under operation Main Generation Projects under Construction Eletrobras Belo Monte 11.233 MW Nov-15 Wind Farms Caiçara I and II, Junco I and II 93 MW Sep-16 Ө Wind Farms Santo Augusto and Santa Joana 390 MW Jan-16 Casa Nova I 180 MW Oct-16 São Manoel May-18 Baraúnas I, Mussambê and Morro Branco I 89 MW Sep-15 700 MW MW R$ Biillion Hydro 21,471.2 77.6 HPU Nuclear 1,405.0 14.9 Wind 1,316.2 5.7 Sinop 400 MW Jan-18 Thermal 589.6 1.1 Total (ELB+SPCs) 24,782.0 99.3 Wind Farms Hermenegildo and Chuí Total ELB 12,741.8 54.2 229 MW Sep-2015 Angra 3 1,405 MW Dec -18 Holding Furnas Wind Farms Capão do Inglês, Coxilha Seca and Galpões 229 MW Aug-2015 Ө Eletronorte Eletrosul Chesf Eletronuclear Amazonas Energia 13