Investor Presentaiton
Teles Pires
1,820 MW
Waiting the
Mauá 3
590 MW
Nov-17
conclusion of the TL
Santo Antônio
3,568 MW
2,286 MW under operation
Jirau
3,750 MW
2,400 MW under operation
Main Generation Projects under Construction
Eletrobras
Belo Monte
11.233 MW
Nov-15
Wind Farms Caiçara I and
II, Junco I and II
93 MW
Sep-16
Ө
Wind Farms Santo
Augusto and Santa Joana
390 MW
Jan-16
Casa Nova I
180 MW
Oct-16
São Manoel
May-18
Baraúnas I, Mussambê
and Morro Branco I
89 MW
Sep-15
700 MW
MW R$ Biillion
Hydro
21,471.2
77.6
HPU
Nuclear
1,405.0
14.9
Wind
1,316.2
5.7
Sinop
400 MW
Jan-18
Thermal
589.6
1.1
Total
(ELB+SPCs) 24,782.0
99.3
Wind Farms
Hermenegildo
and Chuí
Total ELB
12,741.8
54.2
229 MW
Sep-2015
Angra 3
1,405 MW
Dec -18
Holding
Furnas
Wind Farms Capão do Inglês,
Coxilha Seca and Galpões
229 MW
Aug-2015
Ө
Eletronorte
Eletrosul
Chesf
Eletronuclear
Amazonas Energia
13View entire presentation