Investor Presentaiton
•
•
•
•
Greenlink Nevada Transmission Project
Greenlink West
-
Fort Churchill substation to Northwest substation 525 kV
Northwest substation to Harry Allen substation 525 kV
Greenlink North
-
Fort Churchill substation to Robinson Summit substation 525 kV
Common Ties
-
Fort Churchill 525, 345, 230 and 120-kV substation expansion
HUMBOLDT
Greenlink Nevada
PERSHING
WASHOE
Comstock Meadows
Substation
CHURCHILL
Fort Churchill substation to Mira Loma substation 345 kV
-
345-kV Under Development
525-kV Under Development
525-kV In Service
LANDER
STOREY
Mira Loma
Substation
CARSON-
Greenlink North 525 kV
WHITE PINE
EUREKA
Robinson Summit
Substation
Ely
Ft. Churchill
Substation Yerington
DOUGLAS
LYON
Greenlink West 525 kV
-
Fort Churchill substation to Comstock Meadows substation 1 345 kV
Fort Churchill substation to Comstock Meadows substation 2 345 KV
Benefits for customers and the state of Nevada
-
-
-
Creates access to resource-rich renewable energy zones containing
over 5,000 MWs of renewable resources that could not previously be
developed for lack of necessary transmission infrastructure
Facilitates ability to meet Nevada's renewable development and
carbon-reduction goals
Positions Nevada to benefit from renewable energy when future
regional transmission projects interconnect at Robinson Summit
substation
Strengthens electric reliability for Nevada
Aligns with long-term statewide economic growth both in northern and
southern Nevada
Positions Nevada as energy leader in western U.S.
CITY
MINERAL
ESMERALDA
NYE
One Nevada Line 525 kV
Currently in service
LINCOLN
Harry Allen
Substation
Las Vegas
Northwest
Substation
CLARK