Investor Presentaiton

A Look Ahead at Helios Phase 1 (200 MW) Installation of immersion equipment Installation of Core Scientific "swap machines" Installation of Bitmain order Energization Design phase for Intel ASIC-based machines Manufacturing of Intel ASIC-based machines Deployment of Intel ASIC-based machines¹ Q2 2022 Q3 2022 Q4 2022 Q1 2023 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 1. Deployment of Intel ASIC-based machines is based on assumptions for procurement using current production forecasts. The projected timeline could vary due to several factors including supply chain issues, regulatory issues, available capital, and the price of Bitcoin. 9 argo