Investor Presentaiton
Status of CCS/CCUS Projects in Indonesia August 2022
No
Projects
1
Tangguh EGR/CCUS
2
Gundih CCUS/CO2-EGR
3 Sukawati CO2-EOR
Conducted by
bp Berau Ltd., study was conducted
by CoE-ITB
Pertamina, CoE ITB, JGC, J-Power,
JANUS & Supported by METI Japan
Pertamina, LEMIGAS, JAPEX &
Supported by METI Japan
•
Repsol Sakakemang B.V.
Inpex Masela Ltd.
Joint Study Blue Ammonia & CCS Pertamina & PT. Panca Amara
4
CCS Sakakemang
5
Abadi CCS/CCUS
6
in Central Sulawesi
7
8
Study of CCUS for Coal to DME
East Kalimantan CCS/CCUS Study
9
Arun CCS
Utama, JOGMEC, Mitsubishi, ITB
PT. Kaltim Parna Industri & ITB
Pertamina & Chiyoda Corporation
Carbon Aceh & PEMA
Status
FEED Preparation
POD Ubadari dan Vorwata EGR/CCUS has
been approved
Phase-2 Study to mitigate uncertainties &
risks
Subsurface Study by Pertamina
Study CO2-EOR as CCUS by Pertamina,
LEMIGAS, JAPEX
Site selection & characterization
• Preparing Lab test for Feasibility
•
FS with ITB (Completed on July 2022)
JSA Finalization
Preparing required data by Pertamina
Pre-Feasibility Study (surface facilities)
Joint Study Agreement (JSA) has been
signed, Preparing access data & CA
MoU Carbon Aceh-PEMA has been
signed
Preparing for Joint Feasibility Study
(Expected to be started in 2022)
Internal study
Onstream Target
Schedule
2026/2027
2026
■Pilot Test 2026-2027
■Full Scale: 2031
2027
FS (July 2023)
2028
FS (Dec 2023)
2028
CO2 Stored Potential
25 to 33 million tCO2
for 10 to 15 yrs
3 million tCO2 for 10 yrs
7 to 14 million tCO2 for 15
yrs (base case 10
milliontCO2)
30 million tons of CO2
emissions for 15 years
70 million ton of Native CO2
by 2055
19 million tCO2 for 20 yrs
10 million tCO2 for 10 years
26 or 131 million tCO2 for 20
years, depends on scenarios
10
Ramba CCUS (CO2-EOR)
Pertamina
11
Central Sumatera Basin CCS/CCUS
Regional Hubs
Pertamina & Mitsui
East Kalimantan & Sunda Asri
12
13
-
Basin CCS/CCUS Regional Hubs
CO2 Capture & Utilization to
Methanol RU V Balikpapan
14 CCUS Study
Pertamina & Air Liquide
Pertamina & Chevron
2030
Preparing required data & CA
2028
Pertamina & Exxon Mobil
Subsurface Evaluation
2028
15
Pilot Test CO2 Huff and Puff
Jatibarang
JSA has been signed, Joint Study until 2023
Discussion on field candidate, preparing JSA
Validating the simulation result & preparing
2028
Pertamina & Region 2 - Zona 7
injection well, JSA with JOGMEC has been Pilot Test W4 Oct 2022
5
signedView entire presentation