Historical Operating Results and Sustainability Framework
Capital Cost ($M)
Skouries Capital Cost: Evolution from PFS to FS
FS reflects updated input estimates, enhancements, and a more robust execution model
Execution Model - 8%
Updated to reflect an EPCM
delivery model
Includes inflation
adjustment during execution
period
.
Input Costs 7%
Commodity price
increases (steel, copper,
cement, etc.)
Labor cost increases
Scope Enhancements - 5%
.
Water management
Water treatment plant
Diversions & spillways
Treated water re-injection
Foreign Exchange - 3%
Strengthening of the Euro
between development of
PFS and FS
$900
$800
689
$700
$600
$500
$400
$300
$200
$100
33
51
53
$0
PFS
Execution Model
Input Costs
(2018 as presented)
eldorado gold
19
845
Scope Enhancements
FX
Initial Capital Costs
External
Internal