ADB-PLN Electrical Grid Strengthening Program slide image

ADB-PLN Electrical Grid Strengthening Program

| Conventional - PPP Comparison. Conventional Procurement VS PPPS . • • . PLN can meet its transmission needs with conventional borrowing and traditional EPC construction. PLN has the experience, know-how, and staff to build transmission in Indonesia. Total life-cycle costs of the new transmission assets are not fully transparent and difficult to evaluate with government projects. In Brazil, India, Peru, etc., overall value for money judged to be less than that of PPPs. . Indonesia's PPP rules require qualitative & quantitative value-for-money analysis to fully & transparently justify projects. Indonesia's PPP process is time consuming. Preparation plus competition lowers private sector costs but there is local content. PPPs take on (and pay for) many project risks that can increase project costs. Total life-cycle costs often lower than for conventional procurement, which increases value for money. Date 23rd Feb 2021 ADB 10