Corridor 5c: Status of Motorway Sections 3 Section Length, km Financing Secured Status Construction Completion Svilaj-Odzak 11.0 Yes Odzak-Karuse (Republika Srpska) 48.0 No Contractor selected PPP tender ongoing 2014 2017 Karuse-Poprikuse 38.6 No PPP tender ongoing 2018 Poprikuse-Zenica North 18.4 No Preliminary design completed N/A Zenica North-D.Gracanica 3.0 No Main design ongoing N/A D.Gracanica-Klopce 5.5 Yes Issuance of construction permit 2016 Klopce-Drivusa (Zenica South) 2.5 Yes Contractor selection 2016 Drivusa (Zenica South)-Biljesevo 6.5 Yes Under construction 2014 Biljesevo-Kakanj 10.0 Yes Open and operating 2013 Kakanj-Josanica (Sarajevo) 36.6 Yes Open and operating 2012 Josanica-Vlakovo (Sarajevo Bypass) 8.0 Yes Under construction 2014 Vlakovo-Tarcin 20.4 Yes Under construction 2014 Tarcin-Konjic 21.0 No Issuance of construction permit N/A Konjic-Mostar North 47.0 No Preliminary design completed N/A Mostar North-Pocitelj Pocitelj-Zvirovici Zvirovici-Kravice Kravice-Bijaca 37.0 No Preliminary design completed N/A 11.2 No Tender for main design ongoing N/A 5.0 Yes Under construction 2014 Total 5.1 Yes 334.8 Open and operating 2013 AC JP Autoceste FBIH IFC International Finance Corporation World Bank Group
View entire presentation