Corridor 5c: Status of Motorway Sections
3
Section
Length, km
Financing Secured
Status
Construction Completion
Svilaj-Odzak
11.0 Yes
Odzak-Karuse (Republika Srpska)
48.0 No
Contractor selected
PPP tender ongoing
2014
2017
Karuse-Poprikuse
38.6 No
PPP tender ongoing
2018
Poprikuse-Zenica North
18.4 No
Preliminary design completed
N/A
Zenica North-D.Gracanica
3.0 No
Main design ongoing
N/A
D.Gracanica-Klopce
5.5 Yes
Issuance of construction permit
2016
Klopce-Drivusa (Zenica South)
2.5 Yes
Contractor selection
2016
Drivusa (Zenica South)-Biljesevo
6.5 Yes
Under construction
2014
Biljesevo-Kakanj
10.0 Yes
Open and operating
2013
Kakanj-Josanica (Sarajevo)
36.6 Yes
Open and operating
2012
Josanica-Vlakovo (Sarajevo Bypass)
8.0 Yes
Under construction
2014
Vlakovo-Tarcin
20.4 Yes
Under construction
2014
Tarcin-Konjic
21.0 No
Issuance of construction permit
N/A
Konjic-Mostar North
47.0 No
Preliminary design completed
N/A
Mostar North-Pocitelj
Pocitelj-Zvirovici
Zvirovici-Kravice
Kravice-Bijaca
37.0 No
Preliminary design completed
N/A
11.2 No
Tender for main design ongoing
N/A
5.0 Yes
Under construction
2014
Total
5.1 Yes
334.8
Open and operating
2013