NHPC Capacity Addition and Financial Overview
NHPC Standalone Projects Under Clearance
S.
Installed Design
Projects Capacity Energy
Cost
(In Crore)
N.
(MW)
(MUs)
1
Teesta-IV
520
2252
(4x130)
& PL
6113
(Apr'21)
•
•
Sikkim
.
Status
एनएचपीसी
NHPC
•
•
.
•
.
All statutory clearances have been received except forest clearance (stage-II).
Compliance to FRA, 2006 is in progress.
Approval for pre-investment activities received on 03.05.2016.
PIB memo incorporating comments of appraising departments submitted to MoP on 08.04.2022.
Hon'ble Minister of Power and Minister of New & Renewable Energy, Govt of India vide DO letter
dt 09.05.2022 requested Chief Minister of Sikkim for expeditiously resolving the pending issue of
FRA compliance & private land acquisition.
Gram Sabha meeting for Lum-Gor-Sangtok GPU was held on 08.10.2022. Final outcome report is
awaited from District administration.
Hon'ble Chief Minister, Sikkim held a meeting on 28.10.2022 along with Chief Secretary, Addl.
PCCF from State Govt. with CMD, NHPC & other senior officers, in connection with
implementation of Teesta-IV HE Project in Sikkim. Hon'ble Chief Minister assured all support from
Govt. of Sikkim for early implementation of the Project. CMD, NHPC vide DO letter dated
22.12.2022 has appraised the Secretary, Ministry of Power about the issues related to the project.
The period for publication of declaration for acquisition of land for Teesta-IV was extended for
further additional 12 months with effect from 31.12.2022 vide Govt. of Sikkim Notification dated
06.12.2022 in order to complete the process of Section-19.
A meeting was chaired by the Hon'ble Minister of Power and New & Renewable Energy on
16.2.2023 wherein pending issues for obtaining FC-II were discussed. MoM issued by MoP on
22.03.2023. ATR on the minutes of meeting submitted to MoP on 17.04.2023.
Fresh Proposal for Defence clearance uploaded on portal of MoD on 10.05.2023.
⚫ Regular persuasion is being done with State Government for expeditiously resolving the issues of
compliance of Forest Clearance (Stage-II) related to FRA, 2006 and acquisition of 181.06 ha
private & departmental land.View entire presentation