Investor Presentaiton
.
NextGen HydroMet
Molybdenum Plant Update
Feasibility Study completed:
Design of a molybdenum separation plant expected to generate ~6,500tpa of 52% molybdenum concentrate
with a 92% recovery
•
Shipping and logistics parameters confirmed
•
Full load Commissioning expected to be completed - FY221
1,2,3
FS Key Findings
IRR:
Capital cost:
First production:
Estimated By-product credit:
12
3
14.5%
~$95m
CY 2021
around $50/oz
Indicative Plant Layout
Subject to market and operating conditions
Estimates were prepared to a Feasibility Study level with the objective of being subject to an accuracy range of ±15%. Molybdenum is not disclosed in Newcrest's Reserves & Resources
statement, and production average is indicative only and should not be construed as guidance. Additional confirmatory work is required to support molybdenum minerology understanding
and predictability of molybdenum recovery and grade.
AISC calculated assuming average molybdenum production of 4.1m lb p.a with a range of between 80-7000ppm