VSMI
Example of SDG Indonesia One (Development Facilities):
Project Screening Tools for Renewable Energy Power Plant Projects
Collaborative Structure and Schemes
Activities Required for Project Screening Tools
* t....
SDG Indonesia One
Cost Sharing
Development
Bank
Climate
Fund
Donor
SDG Indonesia One Platform
Loan
Lenders
UN
DP
UNDP
Defining Project Screening Tool
Basic Criteria
• Setting basic criteria/1st stage requirement to
be used as preliminary/selection tools to screen
project proposal received by UNDP
•
Setting standard project parties, documentation
and bankable terms and conditions
Standard
Documentation
Technical Assistance for Project Screening Tools
(Role of Advisory team of PT SMI)
FGD
7 Renewable Energy Power Plants
Evaluation
• One on One Meeting and/or FGD to finalize the
basic criteria, Standard Project Parties,
Documentation and Bankable Term &
Conditions.
• Select and evaluate submitted documents from
project sponsor based on basic criteria in
Preparation stage.
AFFORDABLE AND
CLEAN ENERGY
9
INDUSTRY. INNOVATION
CLIMATE
ACTION
17
PARTNERSHIPS
FOR THE GOALS
Finalization
• Perform additional analysis such as
stakeholder discussion, additional support
required, etc. in accordance with bankability
criteria stated by potential lenders.
Provide the Bankable Projects of Renewables Energy that is ready to be Financed by Lenders