Key Investment Highlights
The IEC Transmission Segment
Development plans for 2023-2027 in the transmission segment
■ Addition of appx. 738 circuit km ultra-high voltage transmission lines (400 KV).
■ Establishment of appx. 930 circuit km high voltage transmission lines (161 KV).
חברת החשמל
Israel Electric
Upgrading of appx. 989 circuit km of existing network (high voltage poles) and re-construction of appx. 462
circuit km.
■ Addition of appx. 155 km underground cable circuits.
■ Construction of 3 new switching stations so that by the end of 2025, the total expected capacity in existing
and new 400/161 KV switching stations will be 17,695 MVA.
■ As of the end of 2022, the company has at it's disposal 149 substations with total capacity of 19,486 MVA.
☐
By the end of 2025, the total capacity of the substations is expected to reach 24,849 MVA.
Source: IEC's Financial reports for 2022FY
Investor Relations
25View entire presentation